Construction is in progress!

LAURENT & CLARK
The work is progressing well for the Laurent & Clark project located in the heart of the Quartier des spectacles!
Phase 1: We are in the process of finishing the 18th and 19th floor interior walls, the 5th floor kitchens are now installed, and the bricklaying on Saint-Laurent is coming to an end!
Phase 1 will be ready to welcome its first owners in the fall of 2019!
Phase 2: We are currently excavating the 4th basement.
We are currently at 75% of sales in phase 2, for more information about the project, you can visit at www.laurent-clark.com
BASSIN DU HAVRE
We have now begun the finalizations for the last phase of the Bassins du Havre. The first deliveries will begin at the end of the month!
Phase 4 common spaces will be ready and accessible in the fall, and exterior masonry will be finalized in the next month.
For more information about the project, you can visit the website www.lesbassins.ca
U31
The entrance of the U31 is now finished, we can see the floral patterns before entering phase 3 of the project, and the landscaping will be completed by the arrival of fall!
Phase 4 of the project is moving fast! We are now at the mezzanine floor of the 7th floor and we are starting the construction of the exterior walls this week!
Sales are going very well, and only 3 units are left in phase 4. For more information about the project, you can visit the website www.u31.ca